How Long Does It Really Take to Get a Building Permit in Miami-Dade?

If you’ve ever planned a renovation, repair, or improvement project in South Florida, you already know—permits can make or break your timeline. In Miami-Dade County, even a “simple” building permit can take longer than expected if you don’t prepare properly.

This guide breaks down the Miami-Dade building permit timeline, what factors influence approval speed, and what boards and property owners can realistically expect in 2025.

Whether you’re installing impact windows, renovating a condo lobby, or repairing a roof, understanding the process upfront can save you weeks—and thousands of dollars.

On average, a Miami-Dade building permit can take anywhere from two weeks to three months to approve, depending on project complexity and documentation accuracy.

Small residential permits (like interior remodels or window replacements) are usually processed faster, while commercial or multifamily projects often take longer due to multiple departmental reviews.

But as with most things in Miami, the details matter.

You can verify permit requirements and track applications directly on the Miami-Dade County Permitting Portal.

The timeline starts once your application is submitted through the county’s ePermitting system.

During this stage, county staff checks for completeness—ensuring all forms, plans, and contractor licenses are included. Missing or incorrect information is the number-one reason for delays.

For smaller projects: approvals can take 5–10 business days.
For large or multifamily buildings: expect 2–3 weeks before official review begins.

Pro tip: Upload digital plans in the exact format required. Even one incorrect sheet name or missing engineer stamp can reset your place in line.

Once accepted, your permit will be routed through different departments based on the scope of work. Typical reviews include:

  • Building and structural review – ensures compliance with the Florida Building Code.
  • Zoning – verifies land use, setbacks, and density limits.
  • Environmental and flood compliance – especially critical for coastal areas.
  • Fire and electrical review – mandatory for commercial and high-occupancy properties.

Each department works independently, meaning one delayed review can hold up the entire approval.

You can monitor progress using the Miami-Dade permit status search tool.

Here’s where most applicants underestimate the Miami-Dade building permit timeline.

If reviewers identify errors, you’ll receive a list of “corrections” or “comments” that must be fixed before approval continues. Every resubmission restarts part of the review queue.

Common causes for re-submittal delays include:

  • Incomplete structural calculations.
  • Missing product approvals for impact windows or doors.
  • Incorrect contractor or engineer signatures.
  • Inconsistencies between drawings and application details.

Getting professional help from an experienced project manager—or a property management firm like Cosmo Management Group—can make a major difference here. They ensure everything is complete before submission, preventing costly back-and-forth with the county.

Once all departments sign off, the county issues an approval notice. You’ll then need to pay the remaining fees before the permit is officially released.

The fee structure depends on project type and valuation. You can review the latest Miami-Dade Building Permit Fee Schedule to estimate costs.

After payment, your contractor can download the permit card and begin work.

Getting the permit is only half the process—closing it out properly is equally important.

Each permitted project requires inspections to verify compliance. Skipping or delaying inspections can leave your permit “open,” which becomes a major issue when selling or refinancing the property.

Inspections can be scheduled online via the Miami-Dade inspections portal.

Typical inspection timeframes:

  • Minor projects: 3–5 business days for each inspection.
  • Large projects: 1–3 weeks depending on department backlog.

Once all inspections pass, the permit is closed, and the project is officially complete.

Project TypeAverage Approval TimeNotes
Small interior remodel2–4 weeksSimple scope, minimal reviews
Impact windows/doors3–6 weeksMust include product approvals
Roofing replacement4–6 weeksRequires structural verification
Multifamily upgrades6–12 weeksMultiple departmental reviews
New construction3–6 monthsFull plan review and zoning analysis

These are averages, not guarantees—but they’re useful benchmarks for planning board meetings, budgets, and resident communications.

Several factors can drastically affect your Miami-Dade building permit timeline:

  • Project complexity: The more disciplines involved (electrical, mechanical, plumbing), the longer it takes.
  • Incomplete documentation: The top cause of rejection.
  • Department workload: Seasonal demand spikes during spring and summer.
  • Holidays and hurricane season: County offices experience slowdowns during emergencies.

Many associations overlook one key fact: the county isn’t the only delay. Internal approval from the condo board or homeowners’ association often takes weeks before the permit even reaches the county.

That’s where Cosmo Management Group adds value—by coordinating both internal and external approvals efficiently.

A skilled management partner acts as the bridge between your board, your contractor, and the county. Here’s how a professional like Cosmo keeps your project moving:

  • Reviews all documents before submission to catch errors early.
  • Communicates directly with county reviewers to resolve comments fast.
  • Tracks inspections and maintains compliance records.
  • Keeps owners informed to avoid panic or confusion.

This proactive approach not only shortens the approval timeline but also prevents costly rework or penalties.

A Miami Beach condo board recently hired Cosmo after struggling for five months to secure approval for a balcony repair permit. Within two weeks, Cosmo corrected documentation issues, resubmitted the application, and got approval—saving the board an estimated $15,000 in lost time and contractor rescheduling fees.

The lesson: the right management team can turn a bureaucratic headache into a smooth, predictable process.

The Miami-Dade building permit timeline depends on many factors, but one constant remains—preparation and organization make all the difference.

For boards and property owners, understanding the process isn’t enough; you need a partner who can manage it efficiently from start to finish.

Cosmo Management Group specializes in guiding condo boards and property owners through the permitting maze—ensuring your documentation, communication, and inspections stay on schedule.

Don’t let delays stall your project. Connect with Cosmo to learn how we can simplify the Miami-Dade building permit process, reduce approval times, and help your community complete projects on time and on budget.

1. How long does it take to get a building permit in Miami-Dade County?
It typically takes between 2 weeks and 3 months, depending on project complexity, completeness of documentation, and review backlogs.

2. Can I speed up the Miami-Dade building permit process?
Yes—by submitting complete plans, ensuring licensed contractors are listed, and responding quickly to review comments. Professional management can also help coordinate approvals faster.

3. What causes most delays in Miami-Dade building permits?
Incomplete applications, missing engineer stamps, and miscommunication between departments are the most common causes of delays.

4. How do I check the status of my permit?
Use the official Miami-Dade Permit Tracking Portal to view updates, inspection results, and outstanding requirements.

5. Who can help me manage the permitting process?
A licensed property management company like Cosmo Management Group can coordinate submissions, monitor progress, and handle compliance efficiently to keep your project on schedule.